In fall 2022, the railway siding project connecting the Nepomuk railway station and production area Dvorec has been completed.

Initial evaluation of the construction plan was performed near the end of 2019, project development and preparation of necessary documents took place between September 2020 and January 2022. In March, KLAUS Timber received the construction permit, while the construction work itself began in June. Chládek&Tintěra was the primary supplier. The siding helps reducing truck traffic and, at the same time, it makes the job of load workers less laborious, as they can unload the carriages directly inside the area.